In a traditional design-bid-build project, which of the following is part of the architect’s role?
For a predesign phase, an architect charges an hourly rate of $100, with an upset of $2000, The project ends up taking 30 hours. How much does the architect bill the client for?
While waiting for bids to come in, the architect and the owner realize that there’s an error in the construction documents. This error would seem to exclude one bidder that the owner and architect would like a response from. How should the architect handle this?